Phase 6: Implement instantaneous prediction baselines #446
Labels
No labels
bug
cli
core
docs
event
experiment
figure
invariant
metrics
oracle
phase-0
phase-1
phase-2
phase-3
phase-4
phase-5
phase-6
provenance
revocation
tests
workload
No project
No assignees
1 participant
Notifications
Due date
No due date set.
Blocks
Depends on
#455 Phase 6: Implement probability and threshold validation
erikinkinen/AES
#461 Phase 6: Retrain the fixed feature ablations
erikinkinen/AES
#462 Phase 6: Plan prediction sensitivity fits
erikinkinen/AES
#447 Phase 6: Fit training-only baseline preprocessing
erikinkinen/AES
#448 Phase 6: Fit and export instantaneous logistic baselines
erikinkinen/AES
Reference
erikinkinen/AES#446
Loading…
Reference in a new issue
No description provided.
Delete branch "%!s()"
Deleting a branch is permanent. Although the deleted branch may continue to exist for a short time before it actually gets removed, it CANNOT be undone in most cases. Continue?
Plan ID:
P6-06Record type: Tracking parent; no implementation PR
Scientific protocol: 2.2 · Backlog revision: 2.2.1
Specification: sections 10.4, 10.5.
Source:
AES_PHASES_2_6_PLAN.md, issue heading at line 8149.Plan SHA-256:
8acdaeb52d6a94fcad7de64d64521cd465f608344d63560b45f9202f5af71212Protocol snapshot: Download the complete governing plan.
Goal
establish fair comparisons using current observable information.
Retained requirements
Child issues
Closure
This is an AND tracking parent, not an implementation task. Close it only after every child is accepted and the original parent acceptance below is verified. A permitted
not_applicablechild needs the signed route decision required by section 17.4.baseline model selection has no test access and equal trace
weighting matches the temporal model's objective.
Execution and acceptance contract
Apply the governing semantic/data/statistical contracts in sections 3–5 and the relevant phase section, plus the section-11 checks applicable to this task. Section 17.4 defines the required acceptance evidence. Store the outcome and immutable prerequisite/input/output hashes at
artifacts/backlog/2.2.1/P6-06/acceptance.json.Only explicit dependency and parent-closure edges govern readiness; numbering adds no predecessor dependency. Checkboxes are work/acceptance items, not commit quotas. Keep implementation changes independently reviewable using the existing PR template. Execution, review and gate tasks close with their evidence/decision records and a PR only when tracked artifacts change.
An unsupported scientific effect is a valid result. Missing correctness validation, invalid inference or absent required review is not completion. Do not change endpoints, matrices, margins, inference rules or sample sizes outside the protocol change-control process.
Native blocking dependencies below represent the child-closure requirements; the parent must never block its own children.