CI: full Phase 2 sanitizer suite exceeds the overall 30-minute job budget #655
Labels
No labels
bug
cli
core
docs
event
experiment
figure
invariant
metrics
oracle
phase-0
phase-1
phase-2
phase-3
phase-4
phase-5
phase-6
provenance
revocation
tests
workload
No project
No assignees
1 participant
Notifications
Due date
No due date set.
Blocks
#103 Phase 2: Generate lineage-swap paired tapes
erikinkinen/AES
Reference
erikinkinen/AES#655
Loading…
Reference in a new issue
No description provided.
Delete branch "%!s()"
Deleting a branch is permanent. Although the deleted branch may continue to exist for a short time before it actually gets removed, it CANNOT be undone in most cases. Continue?
Reproduction
PR #652 at
f9b114fa0d5d3d9ce1530d7941af61083bd9c0fbintegratesaccepted #653, running all 192 tests with Clang 19 Debug
-g -O1, ASan/UBSanand one CTest worker. Both sanitizer jobs hit the overall job deadline:
context deadline exceededat 2026-10-21 01:12:31 UTC.at 2026-10-21 01:12:30 UTC.
attempts. Remaining tests were not executed, so neither run is accepted.
each under sanitizers. Cold setup/build and the enlarged sequential suite
together exceed the 30-minute allowance. Smoke cases take approximately
54–58 seconds each. These observations do not identify a unique slowdown cause.
This is a separate overall-capacity regression from #653's per-test timeouts.
Retain complete logs and exact-head status before changing the workflow.
Fix and scope
Set an explicit 90-minute overall budget for both full-suite CI jobs. The
observed 192-test run already needs more than 30 minutes; the prepared second
100-test generator family adds comparable work. Ninety minutes is a bounded
engineering allowance for these complete sequential suites and cold builds,
not an empirical runtime guarantee. Keep the complete inventory, one CTest
worker, compiler/container,
-g -O1, assertions, ASan/UBSan and the sanitizer120-second per-test timeout unchanged. No test filtering, retries, disabled
checks, scientific changes or shortened workloads are allowed.
Steps
Definition of done
Use one signed branch and PR for this bug. Integrate its final candidate into
#652 with explicit source/provenance checks, and run that expanded consumer's
full remote checks. Require all eight checks on both heads before checking this
bug or merging its fix. Then require #652's closed prerequisites and exact-head
checks before checking #103 and merging. Preserve original failed evidence and
new successful logs. The baseline 92-test checks alone do not demonstrate
expanded-suite capacity. Any further real failure remains a failed gate and
receives a separate diagnosis/issue.